Idaho firm acquiring Geysers site

SONOMA COUNTY and LAKE COUNTY -- U.S. Geothermal Inc, a geothermal energy company with offices in Boise, Idaho, has announced plans to acquire a late stage development at the Geysers that has shown promise for enough steam production to power up to 26,000 homes.

Currently under ownership of Reno, Nev.-based Ram Power Corp., the project, encompassing 3,800 acres, includes permits and design plans for a proposed power plant and five production-ready geothermal steam wells. U.S. Geothermal announced an agreement to buy the project for $6.4 million in cash, acquiring assets and subsidiaries associated with its development and leasing of related lands.

The sale is expected to close on or before April 30, according to announcements from the companies.

Ram and its subsidiary, Western GeoPower, have collectively invested over $90 million in the site since Western GeoPower first began researching its potential as an independent company in 2006, according shareholder reports from Ram. The Western GeoPower subsidiary will transfer to U.S. Geothermal in the sale. The company does not break down its employment by subsidiary, but had 122 employees overall at the end of 2013.

Ram could not be reached for comment on the sale, but noted an overall desire to refocus resources on other existing projects as part of its 2013 annual report.

"We committed to monetizing the Geysers project, which frees additional capital into the company allowing for the strategic process to be completed in 2014," said Antony Mitchell, Ram's executive chairman, in an announcement of the sale.

Ram's decision to sell the project despite those expenditures highlights the current economics of new plant construction in the world of geothermal power, where relatively expensive facilities must compete on a per-megawatt basis against sources with a cheaper cost of entry, said Ken Speer, assistant general manager of generation at the Northern California Power Agency. The plant was to be the first new facility at the Geysers in 25 years, an area where a handful of companies produces around 800 megawatts of power across nearly 20 power plants.

The NCPA, which itself owns and operates four geothermal power facilities at the Geysers, agreed in 2008 to purchase all power produced at the site for 20 years at a cost of $520 million. A revised power purchase agreement in 2011 to support the feasibility of the project expired in March of 2013.

"As Ram went in and tried to develop -- even at the higher power purchase price, it wasn't going to be profitable," Mr. Speer said.

Western GeoPower had originally estimated wells at the site to be sufficient for more than 30 megawatts of production, but revised that estimate downward as exploratory drilling continued in the following years.