Bills aim to fix California’s long delays in connecting construction projects to the grid
Significant delays in connecting construction projects to the power grid are emerging at hundreds of projects in the North Coast and across California, raising alarms for some state lawmakers who fear long delayed or abandoned projects will harm local economies.
The issue, which also threatens the state’s accelerating push to add housing and shift to zero-carbon energy, has spawned a flurry of recent bills in Sacramento aiming to not only to define the scope of the problem but also to push utilities and their regulators to fix them.
On Friday, State Sen. Scott Wiener, D-San Francisco, updated his Senate Bill 82, introduced Jan. 13, to require utilities to hook up power to a new or existing development project within eight weeks of its getting a local government go-head to do so.
If the utility doesn’t meet that timeframe, it would have to pay a penalty to the project applicant, according to a news release on the update.
As of February, Pacific Gas & Electric Co. had tracked 134 construction-ready projects — with hundreds of housing units and other “critical priorities” — that had been awaiting the state’s largest investor-owned utility’s completion of their interconnections to the electrical grid for longer than eight weeks, according to a data request obtained by Wiener’s office.
Of those projects, 95 had been waiting more than 12 weeks, and some affordable-housing projects have been kept waiting over a year and a half. Eighty of the projects are multifamily properties, mostly in Santa Clara, San Francisco, San Mateo and Alameda counties.
Sonoma Clean Power, a power provider for customers in Sonoma and Mendocino counties across PG&E’s lines, told the Business Journal that local permitting agencies reported “unusually long delays” to secure electricity interconnections to hundreds of homes and buildings across the state.
In the North Bay, two such local projects include two additional warehouses at the Billa Landing development near Sonoma County airport and a 477,000-square-foot, four-warehouse project in Shiloh Business Park along the west side of Highway 101 also by the airport.
As the Business Journal reported in October, at issue for both projects is needed capacity and distribution-line upgrades at PG&E’s Fulton substation just south of the airport industrial area. In December, the timeframe for completion of the upgrades was mid-2024, and now the utility is telling current applicants for interconnections that the new capacity is anticipated by the end of that year, a spokesperson told the Journal.
“Timelines are subject to change based on emergency and other priority work,” wrote spokesperson Lynsey Paulo in an email.
At Billa Landing, the project team is figuring out in coming weeks whether to pursue some form of temporary alternative power that would allow the buildings to get a local-government green light for occupancy as basic warehouses, rather than electricity-heavy uses such as indoor cannabis cultivation or related production, according to project general contractor Nordby Construction of Santa Rosa.
“General warehouses do not have a lot of power requirements, especially with the new LED lighting,” said Craig Nordby, CEO.
If it’s not economically feasible to hook up another energy source until the full interconnect is completed, then the project may be put on hold, he said.
At the Shiloh Business Park project, the goal remains to break ground on all the buildings this summer then complete them in the third quarter of next year, according to project general contractor Devcon Construction. The project team submitted its application for interconnection a year ago and was told to check in again after the developers, Brennan Investment Group and New York Life, purchased the 75-acre property, which happened in September.
That’s when the team started to hear rumors about interconnection delays in the airport area. The word from PG&E was that alternative power wouldn’t be needed to fit the project timeline, as the late 2024 estimate for Fulton substation upgrade completion would work, said Danny Garon, North Bay project manager.
“Officially, we haven’t slowed our schedule yet,” Garon said Danny Garon, North Bay project manager.
The usual process for power interconnections for commercial buildings Devcon has worked on take less than a year form application to electrification, Garon said. The typical process after application involves hearing from the PG&E technical team within a couple of weeks then payment of a fee to cover the utility’s engineering design. A recent major North Bay project for Devcon was the Straus Family Dairy facility in an existing Rohnert Park industrial building, and that took less than a year from application to completed interconnection.